Installation and Torquing at Height

Controlled assembly of steel, mechanical and electronic equipment in hard-to-reach points.

Installation and positioning of the facade panel — CBRT Tower
The team working at the assembly level of the front elements at the CBRT site.

Scope of service

In high-altitude installation operations, load control, tool safety and application order are as important as access technique. Olimpos creates the reach, lift and torque plan together according to the mounting point and the features of the part.

Application support for main contractors and technical operation teams who need equipment installation, connection control and torqueing on facades, steel construction, towers, facilities or high ceilings.

  • Mounting point specific access scenario
  • Precautions against falling tools and materials
  • Controlled torque and connection application
  • Application records and delivery report

Application areas

Steel construction connections

Lighting, camera and sensor installation

Signboard and facade elements

Mechanical equipment and pipe supports

When is this service suitable?

If the crane or platform cannot approach

Floor, façade geometry or plant equipment may limit machine access to the working point.

If the part requires controlled transportation

Equipment weight, lifting route, attachment sequence and tool safety are planned together.

If registered torque of the connections is desired

A delivery record can be created by following the application points with equipment appropriate to the scope of work.

If the interruption of the operation is limited

Installation work can be divided into stages according to the usage hours of the building or facility.

Work methods and safety

Access and removal plan

Rope lines, material route, backup and connection points are determined before application.

Tool and part safety

Hand tools and assembly parts are backed up against falling; The sub-area is organized as a controlled work zone.

Controlled connection

The assembly sequence, manufacturer or project requirements, and torque values, if applicable, are coordinated with the field team.

Working order from site survey to delivery

  1. Technical evaluation

    Part, connection point, height, access and project documents are examined.

  2. Operation preparation

    The team, rope lines, lifting equipment, teams and sub-area plan are prepared.

  3. Assembly and control

    The application is executed in a controlled manner according to the specified sequence and connection requirements.

  4. Delivery record

    Completed points are checked; Photographs and torque records are prepared within the scope.

Limits of work in mechanical assembly with rope access

We worked on the installation of facade modules and sunshades at the CBRT Tower. At THY Cargo Buildings, our duty was to provide rope access to the technical team who would make repairs in hard-to-reach mechanical installation points.

In the quote request, state who will supply the part, who will make the connection, and whether you want access support only or assembly as well. If torquing is desired, include the connection list, approved torque values ​​if any, and expected delivery record.

What you can share for site survey

  • Parts list, dimensions/weight and connection drawings
  • Material supply, access and installation responsibilities
  • Approved torque values, point list and delivery format, if applicable

How to prepare a proposal?

For the final offer, access conditions and the work to be done are evaluated together. The main issues affecting the cost of this service are:

Part and connection specifications

Weight, size, connection type and torque requirement affect equipment layout.

Access and removal route

Roof access, anchors, working height and part transport distance are evaluated.

Piece and field schedule

The number of assembly points, shifts, leave and mobilization conditions determine the duration.

Reporting need

The scope of photo delivery, point list and torque records is defined in the quotation.

Frequently asked questions

What equipment can be installed with rope access?

Facade elements, signboards, lighting, cameras, sensors, cable carriers and suitable mechanical parts can be evaluated. Part weight and assembly conditions are examined during site survey.

Can torque values ​​be recorded?

Depending on the project scope and the equipment to be used, application points, target values ​​and completion records can be recorded in the delivery document.

Can heavy items be carried by rope?

For each piece, weight, lifting route, anchorage capacity and rescue approach are evaluated separately. For unsuitable loads, a crane or other method is planned.

Is the area completely closed during installation?

The lower area is checked against the risk of material falling. The area and time to be covered are limited as much as possible by the work stages.

How is the installation price at height calculated?

Part properties are calculated after site survey based on quantity, access setup, connection method, working hours and reporting scope.

ON SITE

Our work on site.

Installation examples on facade panels, metal connections and sign holders. The photos show the position of the part at the point of operation.

All photos

Useful information for planning.